Logo
Media release
Unaudited interim results
for the six months ended 30 June 2024

REVIEW OF OPERATIONS Review of Operations

Quarter ended 30 June 2024 compared with quarter ended 31 March 2024

Figures may not add as they are rounded independently

Gruyere

    June
2024
March
2024
%
Variance
Mine physicals and AIC in table on a 100% basis        
Ore mined 000 tonnes 1,052 1,023 3 %
Waste (Capital) 000 tonnes 9,219 7,312 26 %
Waste (Operational) 000 tonnes 39 254 (85)%
Total waste mined 000 tonnes 9,258 7,566 22 %
Total tonnes mined 000 tonnes 10,310 8,589 20 %
Grade mined g/t 1.33 1.32 1 %
Gold mined 000'oz waste/ 44.8 43. 4 3 %
Strip ratio ore 8.8 7.4 19 %
Tonnes milled 000 tonnes 2,082 1,938 7 %
Yield g/t 0.93 1.03 (10)%
Gold produced 000'oz 62.5 64.3 (3)%
Gold sold 000'oz 62.4 64.7 (4)%
AIC and capital in table on a 50% basis        
AISC A$/oz 2,691 2,639 (2)%
US$/oz 1,774 1,737 (2)%
AIC A$/oz 2,707 2,647 (2)%
US$/oz 1,784 1,742 (2)%
Sustaining capital expenditure A$m 28.8 26.2 10 %
US$m 19.0 17.2 10 %
Non-sustaining capital expenditure A$m – %
US$m – %
Total capital expenditure A$m 28.8 26.2 10 %
US$m 19.0 17.2 10 %

The significant rainfall event in March 2024 which resulted in the closure of the Great Central Road, the primary access road to Gruyere, from 5 March 2024 to 30 April 2024 significantly impacted production in both the March and June quarters. Improved production is forecast for the second half of 2024.

Gold production decreased by 3% to 62,500oz in the June quarter from 64,300oz in the March quarter due to the lower grade of ore processed.

AIC increased by 2% to A$2,707oz (US$1,784/oz) in the June quarter from A$2,647oz (US$1,742/oz) in the March quarter.

Total capital expenditure (on a 50% basis) increased by 10% to A$29m (US$19m) in the June quarter from A$26m (US$17m) in the March quarter following increased waste stripping at Stage 5 of the Gruyere pit.

Granny Smith

    June
2024
March
2024
%
Variance
         
Underground ore mined 000 tonnes 373 395 (6) %
Underground waste mined 000 tonnes 140 106 32 %
Total tonnes mined 000 tonnes 513 501 2 %
Grade mined – underground g/t 5.86 5.24 12 %
Gold mined 000’oz 70.2 66.5 6 %
Tonnes milled 000 tonnes 360 389 (7)%
Yield g/t 5.55 4.93 13 %
Gold produced 000'oz 64.2 61.7 4 %
Gold sold 000'oz 72.9 53.0 38 %
AISC A$/oz 1,802 2,051 12 %
US$/oz 1,188 1,350 12 %
AIC A$/oz 1,997 2,299 13 %
US$/oz 1,316 1,512 13 %
Sustaining capital expenditure A$m 22.5 15.8 42 %
US$m 14.8 10.4 42 %
Non-sustaining capital expenditure A$m 13.3 12.2 9 %
US$m 8.7 8.0 9 %
Total capital expenditure A$m 35.8 28.0 28 %
US$m 23.5 18.4 28 %

Gold production increased by 4% to 64,200oz in the June quarter from 61,700oz in the March quarter due to higher grades mined.

AIC decreased by 13% to A$1,997/oz (US$1,316/oz) in the June quarter from A$2,299/oz (US$1,512/oz) in the March quarter as a result of higher gold sold and lower production costs on decreased ore mined and processed, which was partially offset by increased capital expenditure.

Total capital expenditure increased by 28% to A$36m (US$24m) in the June quarter from A$28m (US$18m) in the March quarter with increased expenditure on underground development and infrastructure.

St Ives

  June
2024
March
2024
%
Variance
Underground        
Ore mined 000 tonnes 423 407 4 %
Waste mined 000 tonnes 210 168 25 %
Total tonnes mined 000 tonnes 633 575 10 %
Grade mined g/t 4.19 4.22 (1)%
Gold mined 000’oz 57.0 55.3 3 %
Surface        
Ore mined 000 tonnes – %
Waste (Capital) 000 tonnes 2,659 2,428 10 %
Waste (Operational) 000 tonnes – %
Total waste mined 000 tonnes 2,659 2,428 10 %
Total tonnes mined 000 tonnes 2,659 2,428 10 %
Grade mined g/t – %
Gold mined 000’oz – %
Strip ratio waste/
ore
– %
Total (underground and surface)        
Total ore mined 000 tonnes 423 407 4 %
Total grade mined g/t 4.19 4.22 (1)%
Total tonnes mined 000 tonnes 3,292 3,003 10 %
Total gold mined 000’oz 57.0 55.3 3 %
Tonnes milled 000 tonnes 1,039 1,011 3 %
Yield – underground g/t 3.03 4.18 (28)%
Yield – surface g/t 0.99 0.70 41 %
Yield – combined g/t 2.10 2.12 (1)%
Gold produced 000’oz 70.1 68.9 2 %
Gold sold 000’oz 71.4 73.8 (3)%
AISC A$/oz 2,903 2,753 (5)%
US$/oz 1,913 1,811 (6)%
AIC A$/oz
3,132 2,954 (6)%
US$/oz 2,064 1,943 (6)%
Sustaining capital expenditure A$m 56.8 48.3 18 %
US$m 37.4 31.8 18 %
Non-sustaining capital expenditure A$m 10.2 8.6 19 %
US$m 6.8 5.7 19 %
Total capital expenditure A$m 67.0 56.9 18 %
US$m 44.2 37.5 18 %

Gold production increased by 2% to 70,100oz in the June quarter from 68,900oz in the March quarter due to increased ore mined and processed from the underground mines. In line with the mine plan, production is expected to increase in the second half of the year as the Swiftsure and Invincible Footwall South open pits transition from pre-strip to ore production.

AIC increased by 6% to A$3,132/oz (US$2,064/oz) in the June quarter from A$2,954/oz (US$1,943/oz) in the March quarter due to increased capital expenditure and a decrease in gold sold.

Total capital expenditure increased by 18% to A$67m (US$44m) in the June quarter from A$57m (US$38m) in the March quarter with increased expenditure on the Renewables Power Project.

Agnew

  June
2024
March
2024
%
Variance
Underground        
Ore mined 000 tonnes 315 280 13 %
Waste mined 000 tonnes 237 139 71 %
Total tonnes mined 000 tonnes 552 419 32 %
Grade mined g/t 5.54 6.36 (13)%
Gold mined 000’oz 56.0 57.2 (2)%
Surface        
Waste (Capital) 000 tonnes 626 (100)%
Waste (Operational) 000 tonnes (100)%
Total waste mined 000 tonnes 626 (100)%
Total tonnes mined 000 tonnes 626 (100)%
Grade mined g/t – %
Gold mined 000’oz – %
Total (underground and surface)        
Total ore mined 000 tonnes 315 280 13 %
Total grade mined g/t 5.54 6.36 (13)%
Total tonnes mined 000 tonnes 551 1,045 (47)%
Total gold mined 000’oz 56.0 57.2 (2)%
Tonnes milled 000 tonnes 313 288 9 %
Yield – underground g/t 5.66 5.76 (2)%
Yield – surface g/t – %
Yield – combined g/t 5.66 5.76 (2)%
Gold produced 000’oz 57.0 53.3 7 %
Gold sold 000’oz 59.3 53.7 10 %
AISC A$/oz 2,110 2,002 (5)%
US$/oz 1,390 1,317 (6)%
AIC A$/oz
2,303 2,258 (2)%
US$/oz 1,518 1,486 (2)%
Sustaining capital expenditure A$m 23.5 17.1 37 %
US$m 15.5 11.2 38 %
Non-sustaining capital expenditure A$m 9.0 7.8 15 %
US$m 5.9 5.1 16 %
Total capital expenditure A$m 32.5 24.9 31 %
US$m 21.4 16.3 31 %

Gold production increased by 7% to 57,000oz in the June quarter from 53,300oz in the March quarter due to increased underground ore mined and processed.

Total tonnes mined decreased by 47% quarter on quarter due to the inclusion of 626kt of surface capital waste mined at the Barren Lands pit in the March quarter. This represented works on a minor cutback at the east wall of the pit to ensure long-term pit stability while being utilised to provide access to the Barren Lands and Redeemer Underground Complexes.

AIC increased by 2% to A$2,303/oz (US$1,518oz) in the June quarter from A$2,258/oz (US$1,486oz) in the March quarter on higher capital expenditure partially offset by increased gold sold.

Total capital expenditure increased by 31% to A$33m (US$21m) in the June quarter from A$25m (US$16m) in the March quarter due to increased development at Waroonga and Redeemer.

South Deep

  June
2024
March
2024
%
Variance
Ore mined 000 tonnes 445 334 33 %
Waste mined 000 tonnes 99 110 (10)%
Total tonnes 000 tonnes 544 444 23 %
Grade mined – underground reef g/t 5.53 5.25 5 %
Grade mined – underground total g/t 4.52 3.95 14 %
Gold mined kg 2,459 1,753 40 %
000’oz 79.1 56.4 40 %
Development m 3,206 2,934 9 %
Secondary support m 2,557 2,103 22 %
Backfill m3 153,382 109,633 40 %
Ore milled – underground reef 000 tonnes 418 345 21 %
Ore milled – underground waste 000 tonnes 53 70 (24)%
Total underground tonnes milled 000 tonnes 471 415 13 %
Ore milled – surface 000 tonnes 282 314 (10)%
Total tonnes milled 000 tonnes 753 729 3 %
Yield – underground reef g/t 4.28 5.13 (17)%
Surface yield g/t 0.10 0.14 (29)%
Total yield g/t 2.41 2.49 (3)%
Gold produced kg 1,818 1,814 – %
000’oz 58.5 58.3 – %
Gold sold kg 1,855 1,666 11 %
000’oz 59.6 53.5 11 %
AISC R/kg 1,149,439 1,144,350 – %
US$/oz 1,924 1,886 (2)%
AIC R/kg 1,149,439 1,144,350 – %
US$/oz 1,924 1,886 (2)%
Sustaining capital expenditure Rm 483.4 340.9 42 %
US$m 26.0 18.1 44 %
Non-sustaining capital expenditure Rm – %
US$m – %
Total capital expenditure Rm 483.4 340.9 42 %
US$m 26.0 18.1 44 %

A number of key production parameters improved from the March to the June quarter, however, gold produced remained similar at 1,818kg (58,500oz) in the June quarter from 1,814kg (58,300oz) in the March quarter.

Total development increased by 9% in the June quarter to 3,206m from 2,934m in the March quarter as improved efficiencies were realised from HP drill rigs owing to maturing cuts and increased end availability. Total tonnes mined in the June quarter increased by 23% to 544kt from 444kt in the March quarter. Improved volumes were driven by additional equipment coming into production, improved equipment reliability, utilisation and by improvements in the mining efficiencies. Reef grade mined increased by 5% to 5.53g/t in the June quarter from 5.25g/t in the March quarter driven by the changing mining footprint. Backfill placed increased by 40% to 153,382m3 in the June quarter from 109,663m3 in the March quarter as stopes became available for backfilling.

Total underground tonnes milled increased by 13% to 471kt in the June quarter from 415kt in the March quarter due to increased mining volumes. Surface tonnes processed decreased by 10% to 282kt in the June quarter from 314kt in the March quarter due to lower operating hours as a result of planned maintenance of a CIL tank.

Reef yield decreased by 17% to 4.28g/t in the June quarter from 5.13g/t in the March quarter due to a lower-than-planned mine call factor (MCF). Surface yield decreased by 29% to 0.10g/t in the June quarter from 0.14g/t in the March quarter as high-grade surface clean-up material was depleted, the current yields are in line with the business plan.

AIC remained flat at R1,149,439/kg (US$1,924/oz) in the June quarter from R1,144,350/kg (US$1,886/oz) in the March quarter.

Total capital expenditure increased by 42% to R483m (US$26m) in the June quarter from R341m (US$18m) in the March quarter. The increase is mainly due to higher mobile equipment refurbishments, Collision Avoidance System (CAS) level 9 implementation on underground mobile equipment, higher spend on underground fixed infrastructure (roadways, waste rock aggregate plant, tips), purchasing of underground steel handling equipment and annual Microsoft licencing in the June quarter.

Damang

      June
2024
March
2024
%
Variance
Tonnes milled   000 tonnes 1,236 1,240 – %
Yield   g/t 0.94 0.87 8 %
Gold produced   000’oz 37.3 34.6 8 %
Gold sold   000’oz 37.9 33.5 13 %
AISC   US$/oz 1,787 2,063 13 %
AIC   US$/oz 1,787 2,063 13 %
Sustaining capital expenditure   US$m 1.8 2.9 (38)%
Non-sustaining capital expenditure   US$m – %
Total capital expenditure US$m 1.8 2.9 (38)%

Gold production increased by 8% to 37,300oz in the June quarter from 34,600oz in the March quarter due to higher yield. Yield increased by 8% to 0.94g/t in the June quarter from 0.87g/t in the March quarter due to improved MCF from the historic stockpiles fed.

AIC decreased by 13% to US$1,787/oz in the June quarter from US$2,063/oz in the March quarter mainly due to higher gold sold and lower capital expenditure.

Total capital expenditure decreased by 38% to US$2m in the June quarter from US$3m in the March quarter due to timing of expenditure on the Far East Tailings Storage Facility Stage 4 raise project.

Tarkwa

    June
2024
March
2024
%
Variance
Ore mined 000 tonnes 3,600 3,314 9 %
Waste (Capital) 000 tonnes 9,406 9,357 1 %
Waste (Operational) 000 tonnes 11,446 9,749 17 %
Total waste mined 000 tonnes 20,852 19,106 9 %
Total tonnes mined 000 tonnes 24,452 22,420 9 %
Strip ratio waste/ore 5.4 5.8 (7)%
Grade mined g/t 1.06 1.27 (17)%
Gold mined 000’oz 122.5 135.6 (10)%
Tonnes milled 000 tonnes 3,667 3,683 – %
Yield g/t 0.98 1.11 (12)%
Gold produced 000’oz 115.9 131.8 (12)%
Gold sold 000’oz 120.8 127.3 (5)%
AISC US$/oz 1,897 1,751 (8)%
AIC US$/oz 1,897 1,751 (8)%
Sustaining capital expenditure US$m 57.9 54.4 6 %
Non-sustaining capital expenditure US$m – %
Total capital expenditure US$m 57.9 54.4 6 %

Gold production decreased by 12% to 115,900oz in the June quarter from 131,800oz in the March quarter due to lower yield as a result of increased ex-pit volumes at lower grades and increased volumes of lower grade stockpiled material. Waste stripping to unlock ore increased and key ore blocks are expected to be exposed in Q3 2024.

Total tonnes mined, including capital waste stripping, increased by 9% due to increased mining capacity and to prioritise waste stripping to unlock key ore blocks.

AIC increased by 8% to US$1,897/oz in the June quarter from US$1,751/oz in the March quarter due to lower gold sold, higher royalties and higher capital expenditure.

Total capital expenditure increased by 6% to US$58m in the June quarter from US$54m in the March quarter due to higher tailings project construction expenditure of US$9m in the June quarter compared to US$5m in the March quarter.

Chile

Salares Norte

    June
2024
March
2024
%
Variance
         
Ore mined 000 tonnes 1,415 (100)%
Waste (capital) 000 tonnes 8,388 6,637 26 %
Waste (operational) 000 tonnes 1,741 (100)%
Total waste mined 000 tonnes 8,388 8,378 – %
Total tonnes mined 000 tonnes 8,388 9,793 (14)%
Strip ratio waste/ore 5.92 (14)%
Grade mined – gold g/t 4.61 (100)%
Grade mined – silver g/t 136.55 (100)%
Gold mined 000’oz 209.8 (100)%
Silver mined 000’oz 6,210.3 (100)%
Tonnes milled 000 tonnes 12 4 200 %
Gold recoveries per cent 0.2 100 %
Silver recoveries per cent 0.2 100 %
Yield – Gold g/t 1.3 100 %
– Silver per cent 6.4 100 %
– Combined eq g/t 1.3 100 %
Gold produced 000’oz 0.5 100 %
Silver produced 000’oz 2.4 100 %
Total equivalent gold produced 000’eq oz 0.5 100 %
Total equivalent gold sold 000’eq oz 0.5 100 %
AISC US$/oz 74,677 100 %
AISC US$/ eq oz 70,142 100 %
AIC US$/oz 206,790 100 %
AIC US$/ eq oz 193,973 100 %
Sustaining capital expenditure US$m 35.1 22.7 55 %
Non-sustaining expenditure US$m 61.4 111.1 (45)%
Total capital expenditure US$m 96.5 133.8 (28)%

Processing plant ramp-up continued during the June quarter but continued to be negatively impacted by severe weather events. Gold production was 468oz in the June quarter compared to 19oz in the March quarter and silver production increased to 2,382oz in the June quarter from 93oz in the March quarter. Gold-equivalent production increased to 497oz in the June quarter from 20oz in the March quarter. The first sales for Salares Norte were completed during the June quarter.

Total capital expenditure decreased by 28% to US$97m in the June quarter from US$134m in the March quarter as construction activities were largely completed and demobilisation of contractors commenced during the June quarter.

Peru

Cerro Corona

    June
2024
March
2024
%
Variance
         
Ore mined 000 tonnes 3,167 1,934 64 %
Waste mined 000 tonnes 3,357 2,771 21 %
Total tonnes mined 000 tonnes 6,524 4,705 39 %
Strip ratio waste/ore 1.1 1.4 (21)%
Grade mined – gold g/t 0.44 0.49 (10)%
Grade mined – copper per cent 0.32 0.35 (9)%
Gold mined 000’oz 44.5 30.3 47 %
Copper mined 000 tonnes 10,281 6,693 54 %
Tonnes milled 000 tonnes 1,433 1,590 (10)%
Gold recovery per cent 71.4 71.4 – %
Copper recovery per cent 89.7 88.6 1 %
Yield – Gold g/t 0.38 0.41 (7)%
– Copper per cent 0.34 0.35 (3)%
– Combined eq g/t 0.79 0.82 (4)%
Gold produced 000’oz 16.8 20.2 (17)%
Copper produced tonnes 4,707 5,371 (12)%
Total equivalent gold produced 000’eq oz 36.5 42.0 (13)%
Total equivalent gold sold 000’eq oz 37.9 41.7 (9)%
AISC US$/oz 546 1,076 49 %
AISC US$/ eq oz 1,498 1,548 3 %
AIC US$/oz 672 1,116 40 %
AIC US$/ eq oz 1,557 1,568 1 %
Sustaining capital expenditure US$m 4.5 5.4 (17)%
Non-sustaining capital expenditure US$m 0.2 0.1 100 %
Total capital expenditure US$m 4.7 5.5 (15)%

Gold-equivalent production decreased by 13% to 36,500oz in the June quarter from 42,000oz in the March quarter, mainly due to lower gold and copper grades processed in line with the mine sequence and as result of lower tonnes milled due to ore hardness.

AIC per gold ounce sold decreased by 40% to US$672/oz in the June quarter from US$1,116/oz in the March quarter, mainly due to higher by-product credit resulting from a higher copper price and a higher gold inventory credit to cost on the back of the higher low-grade ore mined and stockpiled during the dry season. This was partially offset by lower gold ounces sold.

Total capital expenditure decreased by 15% to US$5m in the June quarter from US$6m in the March quarter, driven by the TSF Water Treatment Plant construction plan.