Australia region
St Ives
|
|
|
|
Six months ended |
|
|
Gold produced |
000’oz |
|
187.6 |
|
189.8 |
|
|
Gold sold |
000’oz |
|
183.2 |
|
190.2 |
|
|
Yield |
– underground |
g/t |
|
3.91 |
|
4.16 |
|
|
|
– surface |
g/t |
|
1.99 |
|
2.61 |
|
|
|
– combined |
g/t |
|
2.59 |
|
2.82 |
|
|
AISC – original interpretation |
A$/oz |
|
1,427 |
|
988 |
|
|
|
US$/oz |
|
1,008 |
|
763 |
|
|
AISC – revised interpretation guidance (WGC November 2018) |
A$/oz |
|
1,217 |
|
– |
|
|
|
US$/oz |
|
859 |
|
– |
|
|
AIC |
A$/oz |
|
1,427 |
|
988 |
|
|
|
US$/oz |
|
1,008 |
|
763 |
|
Gold production decreased by 1 per cent from 189,800 ounces for
the six months ended 30 June 2018 to 187,600 ounces for the six
months ended 30 June 2019.
Total tonnes mined decreased by 39 per cent from 13.3 million
tonnes for the six months ended 30 June 2018 to 8.1 million tonnes
for the six months ended 30 June 2019 as ore tonnes mined have
been brought into line with mill capacity and strip ratios have
reduced.
At the underground operations, ore mined increased by 110 per
cent from 0.31 million tonnes for the six months ended 30 June
2018 to 0.65 million tonnes for the six months ended 30 June 2019.
At the Invincible underground mine ore production increased from
0.13 million tonnes to 0.48 million tonnes, following steady state
production levels reached by mid-2018. Ore production from
Hamlet underground mine decreased from 0.19 million tonnes to
0.04 million tonnes, with the mine reaching the end of its life. The
remainder of underground ore was sourced from remnant mining
at Cave Rocks. Total underground grade mined decreased by 11
per cent from 4.53 grams per tonne to 4.05 grams per tonne mainly
due to the grade of ore mined from Invincible underground being
lower than the grade of ore mined at Hamlet during the six months
ended June 2018.
Operational waste tonnes mined from the underground operations
decreased by 22 per cent from 0.23 million tonnes for the six
months ended 30 June 2018 to 0.18 million tonnes for the six
months ended 30 June 2019. Capital waste tonnes mined
increased by 1,300 per cent from 0.02 million tonnes to 0.28 million
tonnes. The decrease in operational waste and increase in capital
waste reflect the increased mining activity at Invincible
underground mine.
At the open pit operations, total ore tonnes mined decreased by
33 per cent from 2.56 million tonnes for the six months ended 30
June 2018 to 1.72 million tonnes for the six months ended 30 June 2019. Ore tonnes mined from Invincible pit decreased by 54 per
cent from 1.54 million tonnes to 0.71 million tonnes. Ore tonnes
mined from Neptune pit remained similar at 1.01 million tonnes for
the six months ended 30 June 2019. Grade mined decreased by
41 per cent from 2.90 grams per tonne to 1.70 grams per tonne
due to the mining of higher grade areas in the Neptune pit during
the six months ended 30 June 2018 and the conclusion of high
grade mining from the Invincible pit during 2018.
Operational waste tonnes mined from the open pit operations
decreased by 55 per cent from 4.25 million tonnes for the six
months ended 30 June 2018 to 1.90 million tonnes for the six
months ended 30 June 2019. Capital waste tonnes mined
decreased by 43 per cent from 6.0 million tonnes to 3.4 million
tonnes. The strip ratio decreased from 4.0 to 3.1. Total open pit
material movement decreased by 45 per cent from 12.8 million
tonnes for the six months ended 30 June 2018 to 7.0 million tonnes
for the six months ended 30 June 2019, with the Invincible pit
becoming deeper and subsequently having a smaller area to mine
and mining operations at Neptune pit scaled down to reduce ore
tonnes mined to mill capacity.
At the consolidated St Ives mine, ounces mined decreased by 37
per cent from 283,500 ounces for the six months ended 30 June
2018 to 177,600 ounces for the six months ended 30 June 2019.
Underground gold mined increased by 84 per cent from 45,600
ounces for the six months ended 30 June 2018 to 84,000 ounces
for the six months ended 30 June 2019. Open pit gold mined
decreased by 61 per cent from 237,900 ounces for the six months
ended 30 June 2018 to 93,600 ounces for the six months ended
30 June 2019, reflecting reduced ore tonnes mined at lower
grades.
By 30 June 2019, Neptune high-grade oxide material stockpiled
amounted to 26,300 ounces (663,000 tonnes at 1.23 grams per
tonne), Invincible amounted to 13,500 ounces (191,900 tonnes at
2.91 grams per tonne) and A5 amounted to 7,900 ounces (174,000
tonnes at 1.46 grams per tonne). This compared with the 30 June
2018, Neptune high-grade oxide material stockpiled amounted to
77,600 ounces (1,142,000 tonnes at 2.34 grams per tonne),
Invincible amounted to 44,500 ounces (375,000 tonnes at 2.81
grams per tonne) and A5 amounted to 7,900 ounces (174,000
tonnes at 1.46 grams per tonne).
Throughput at the Lefroy mill increased by 8 per cent from 2.09
million tonnes for the six months ended 30 June 2018 to 2.25
million tonnes for the six months ended 30 June 2019. Yield
decreased by 8 per cent from 2.82 grams per tonne to 2.59 grams
per tonne due to the lower grade ore mined and processed.
Cost of sales before amortisation and depreciation, increased by
70 per cent from A$102 million (US$78 million) for the six months
ended 30 June 2018 to A$173 million (US$122 million) for the six
months ended 30 June 2019. The higher cost of sales before
amortisation and depreciation was mainly due to increased
underground mining costs associated with the ramp-up of ore
production at Invincible underground of A$16 million (US$11
million) and a gold inventory charge of A$20 million (US$14 million)
for the six months ended 30 June 2019 compared with a gold
inventory credit of A$36 million (US$28 million) for the six months
ended 30 June 2018. The net gold-in-process movement was
A$56 million (US$42 million). The gold inventory movement reflects
the change from a build-up in 2018 to a drawdown of ore
stockpiles in 2019.
Capital expenditure decreased by 3 per cent from A$74 million
(US$57 million) for the six months ended 30 June 2018 to A$72
million (US$51 million) for the six months ended 30 June 2019.
All-in cost increased by 44 per cent from A$988 per ounce
(US$763 per ounce) for the six months ended 30 June 2018 to
A$1,427 per ounce (US$1,008 per ounce) for the six months ended
30 June 2019 mainly due to higher cost of sales before
amortisation and depreciation and lower gold sold, partially offset
by lower capital expenditure.
Agnew
|
|
|
|
Six months ended |
|
|
Gold produced |
000’oz |
|
113.3 |
|
115.4 |
|
|
Gold sold |
000’oz |
|
115.4 |
|
116.9 |
|
|
Yield |
g/t |
|
6.02 |
|
6.11 |
|
|
AISC – original interpretation |
A$/oz |
|
1,753 |
|
1,393 |
|
|
|
US$/oz |
|
1,238 |
|
1,075 |
|
|
AISC – revised interpretation guidance (WGC November 2018) |
A$/oz |
|
1,337 |
|
– |
|
|
|
US$/oz |
|
944 |
|
– |
|
|
AIC |
A$/oz |
|
1,753 |
|
1,393 |
|
|
|
US$/oz |
|
1,238 |
|
1,075 |
|
Gold production decreased by 2 per cent from 115,400 ounces for
the six months ended 30 June 2018 to 113,300 ounces for the six
months ended 30 June 2019.
Ore mined from underground decreased by 4 per cent from
616,600 tonnes for the six months ended 30 June 2018 to 590,700
tonnes for the six months ended 30 June 2019 with reduced
production from the New Holland mine. Head grade mined
decreased by 1 per cent from 6.26 grams per tonne to 6.21 grams
per tonne. In the six months ended 30 June 2019 117,900 ounces
were mined and sourced as follows: 82,500 ounces from
Waroonga (328,300 tonnes at 7.8 grams per tonne) and 35,400
ounces from New Holland (262,400 tonnes at 4.2 grams per tonne).
This compared with 124,000 ounces mined and sourced as
follows: 87,400 ounces from Waroonga (315,000 tonnes at 8.6
grams per tonne) and 36,600 ounces from New Holland (301,000 tonnes at 3.8 grams per tonne) in the six months ended 30 June
2018.
Operational waste tonnes mined from the underground operations
decreased by 17 per cent from 0.12 million tonnes for the six
months ended 30 June 2018 to 0.10 million tonnes for the six months ended 30 June 2019. Capital waste tonnes mined
increased by 11 per cent from 0.27 million tonnes to 0.30 million
tonnes.
Tonnes processed decreased marginally from 587,800 tonnes for
the six months ended 30 June 2018 to 585,600 tonnes for the six
months ended 30 June 2019. The combined yield decreased by 1
per cent from 6.11 grams per tonne to 6.02 grams per tonne in line
with the decrease in head grade mined for the six months ended
30 June 2019.
Cost of sales before amortisation and depreciation, increased by
5 per cent from A$110 million (US$85 million) for the six months
ended 30 June 2018 to A$116 million (US$82 million) for the six
months ended 30 June 2019 mainly due to increased mining cost
at Waroonga, associated with mining at deeper levels in the mine.
The gold-in-process charge to cost of A$3 million (US$2 million)
for the six months ended 30 June 2019 compared with a charge to
cost of A$5 million (US$4 million) for the six months ended 30 June
2018.
Capital expenditure increased by 70 per cent from A$46 million
(US$35 million) for the six months ended 30 June 2018 to A$78
million (US$55 million) for the six months ended 30 June 2019.
Capital expenditure was higher due to A$32 million (US$22 million)
expenditure on a new accommodation village in the six months
ended June 2019. In total A$40 million (US$28 million) has been
spent on the construction of the village and will result in an annual
estimated cost saving of A$10 million (US$7 million). The village
will also reduce commuting time for the Agnew workforce by 40
minutes per day.
All-in cost increased by 26 per cent from A$1,393 per ounce
(US$1,075 per ounce) for the six months ended 30 June 2018 to
A$1,753 per ounce (US$1,238 per ounce) for the six months ended
30 June 2019 due to higher cost of sales before amortisation
depreciation and higher expenditure on the constructing the
Agnew accommodation village.
Granny Smith
|
|
|
|
Six months ended |
|
|
Gold produced |
000’oz |
|
134.0 |
|
137.2 |
|
|
Gold sold |
000’oz |
|
133.9 |
|
137.3 |
|
|
Yield |
g/t |
|
5.10 |
|
5.11 |
|
|
AISC – original interpretation |
A$/oz |
|
1,268 |
|
1,219 |
|
|
|
US$/oz |
|
895 |
|
942 |
|
|
AISC – revised interpretation guidance (WGC November 2018) |
A$/oz |
|
1,029 |
|
– |
|
|
|
US$/oz |
|
727 |
|
– |
|
|
AIC |
A$/oz |
|
1,268 |
|
1,219 |
|
|
|
US$/oz |
|
895 |
|
942 |
|
Gold production decreased by 2 per cent from 137,200 ounces for
the six months ended 30 June 2018 to 134,000 ounces for the six
months ended 30 June 2019 due to decreased tonnes mined and
processed.
Ore mined from underground decreased by 1 per cent from
832,300 tonnes to 824,000 tonnes. Head grade mined decreased
marginally from 5.47 grams per tonne for the six months ended
June 2018 to 5.45 grams per tonne for the six months ended June
2019. Gold mined decreased by 1 per cent from 146,300 ounces
for the six months ended 30 June 2018 to 144,500 ounces for the
six months ended 30 June 2019.
Operational waste tonnes mined from the underground operations
increased by 100 per cent from 0.03 million tonnes for the six
months ended 30 June 2018 to 0.06 million tonnes for the six months ended 30 June 2019. Capital waste tonnes mined
decreased by 14 per cent from 0.28 million tonnes to 0.24 million
tonnes.
Tonnes processed decreased by 2 per cent from 835,700 tonnes
for the six months ended 30 June 2018 to 818,000 tonnes for the
six months ended 30 June 2019 due to the reduction in ore mined
and timing of the campaign milling in the respective periods. Yield
for the six months ended June 2019 at 5.10 grams per tonne
compared to yield of 5.11 grams per tonne for the six months
ended June 2018.
Cost of sales before amortisation and depreciation, increased by
3 per cent from A$105 million (US$81 million) to A$108 million
(US$76 million) due to increased ore development cost of A$3 million (US$2 million) associated with accessing stopes in the
lower levels of the Wallaby mine. Mining cost will remain at a
higher level, with increased material being sourced from Z110 and
Z120, the deepest parts of the mine. The higher cost is associated
with longer haul and travel distances, increased percentage of
ground support requirements and increased tonnes of paste
backfill. A gold inventory credit of A$1 million (US$1 million) for the
six months ended 30 June 2019 compared with a charge of A$nil
million (US$nil million) for the six months ended 30 June 2018.
Capital expenditure decreased by 15 per cent from A$54 million
(US$42 million) for the six months ended 30 June 2018 to A$46
million (US$33 million) for the six months ended 30 June 2019. The
decrease in capital expenditure was primarily due to a reduction in
capital development cost of A$4 million (US$3 million) and a
reduction in exploration costs of A$2 million (US$2 million).
All-in cost increased by 4 per cent from A$1,219 per ounce
(US$942 per ounce) for the six months ended 30 June 2018 to
A$1,268 per ounce (US$895 per ounce) for the six months ended
30 June 2019 mainly due to higher cost of sales before
amortisation and depreciation and lower gold sold, partially offset
by lower capital expenditure.
Gruyere
First gold was poured over the weekend of 29 and 30 June 2019.
The gold was produced from the carbon-in-leach (CIL) and elution
circuits.
With the delivery of first gold, the focus then turned to
commissioning of the final components of the process plant,
particularly the gravity gold circuit and ball mill, which were
completed in July 2019. During the initial stages of ramp-up, lower
grade stockpiled ore is being processed to reduce gold losses
associated with lower recoveries anticipated as the plant
operations are stabilised.
Commencement of the operation of the ball mill marked the start
of an anticipated ramp-up period of six to seven months. Gruyere
is expected to attain commercial production mid-way through the
ramp-up period.
The final forecast capital (FFC) cost estimate remains at A$621
million (level of accuracy range +2 per cent/-2 per cent) as reported
by the joint venture partners on 30 July 2018.
In accordance with the Joint Venture agreement entered into at the
time of the acquisition, Gold Fields will fund up to 10 per cent of
costs overruns, excluding scope changes and force majeure costs.
This translates to approximately A$51 million. Consequently, Gold
Fields' share of the FFC is A$337 million.
Mining activity has delivered 2.5 million tonnes of ore mined
year-to-date and is ahead of plan. Ore delivery comprised 1.3
million tonnes of ore at a grade of 1.04 grams per tonne for
43,000 ounces, and a further 1.2 million tonnes of low grade at
0.61 grams per tonne for 22,000 ounces (100 per cent basis).
|