West Africa region
Ghana
Tarkwa
| |
|
|
June
2012 |
|
March
2012 |
|
| |
Gold produced |
- 000’oz |
176.3 |
|
185.3 |
|
| |
Yield - heap leach |
- g/t |
0.4 |
|
0.5 |
|
| |
- CIL plant |
- g/t |
1.4 |
|
1.5 |
|
| |
- combined |
- g/t |
0.9 |
|
1.0 |
|
| |
Total cash cost |
- US$/oz |
663 |
|
595 |
|
| |
Notional cash expenditure |
- US$/oz |
1,033 |
|
916 |
|
| |
NCE margin |
- % |
36 |
|
45 |
|
Gold production decreased by 5 per cent from 185,300
ounces in the March quarter to 176,300 ounces in the June
quarter due to a decrease in CIL throughput and a lower head
grade delivered to the mill.
Total tonnes mined, including capital stripping, increased from
33.2 million tonnes in the March quarter to 33.6 million tonnes
in the June quarter. Ore mined decreased from 5.9 million
tonnes to 5.8 million tonnes. Mined grade decreased from
1.28 grams per tonne in the March quarter to 1.23 grams per
tonne in the June quarter largely due to scheduling. The strip
ratio increased from 4.6 to 4.8 in line with the plan.
The CIL plant throughput decreased from 2.83 million tonnes
in the March quarter to 2.81 million tonnes in the June quarter
due to reduced mill availability. Yield decreased from 1.51
grams per tonne to 1.45 grams per tonne in line with the
reduction in mined grade. The CIL plant produced 131,400
ounces in the June quarter compared with 137,500 ounces in
the March quarter.
Total feed to the North and South heap leach sections
decreased from 3.18 million tonnes to 3.08 million tonnes.
Yield decreased from 0.47 grams per tonne for the March
quarter to 0.45 grams per tonne in the June quarter. The High
Pressure Grinding Roller facility (HPGR) at the South heap
leach section processed 0.89 million tonnes, compared with
1.04 million tonnes in the March quarter. The North heap
leach section processed 2.19 million tonnes in the June
quarter, compared with 2.14 million tonnes in the March
quarter. The heap leach operation produced 44,900 ounces
compared with 47,800 ounces in the March quarter. The
decrease was attributable to a decrease in tonnes processed
and dissolution due to a harder ore blend.
Operating costs, including gold-in-process movements,
increased from US$106 million (R825 million) in the March
quarter to US$114 million (R917 million) in the June quarter
due to lower inventory build-up. Total cash cost increased
from US$595 per ounce in the March quarter to US$663 per
ounce in the June quarter due to the lower production and
lower inventory build-up.
Operating profit decreased from US$205 million (R1,593
million) in the March quarter to US$171 million (R1,382
million) in the June quarter as a result of the lower revenue
and the increased net operating cost.
Capital expenditure increased from US$47 million (R369
million) in the March quarter to US$60 million (R480 million) in
the June quarter, with expenditure on pre-stripping and
additional mining fleet being the major items.
Capital expenditure increased from R130 million (US$17
million) to R188 million (US$23 million) due to the slow startup
of spend on capital at the beginning of the financial year.
The majority of the capital expenditure was on infrastructure
upgrades and ore reserve development.
Notional cash expenditure increased from US$916 per ounce
in the March quarter to US$1,033 per ounce in the June
quarter due to the decrease in production and increase in
capital expenditure. The NCE margin decreased from 45 per
cent to 36 per cent.
On 16 July, Tarkwa received a directive from the
Environmental Protection Agency (EPA) of Ghana to stop
discharging water from its heap leach facilities.
The new EPA directive requires that all water discharges from
the mine’s heap leach facilities should be treated through a
water treatment plant to reduce conductivity levels.
Conductivity is a measure of the amount of dissolved salts in
discharged water and is classified internationally as a non-toxic
pollutant.
Although we believe that Tarkwa was in full compliance with
all environmental laws and regulations in Ghana, we have, in
pursuit of environmental best practice and world class
environmental stewardship, and to comply with the directive,
committed to installing new water treatment plants before the
end of the year.
On 9 August, the EPA lifted the temporary suspension. Both
heap leach facilities at Tarkwa are now back to full production.
The loss of production for the September quarter is expected
to be around 15,000 ounces.
Damang
| |
|
|
June
2012 |
|
March
2012 |
|
| |
Gold produced |
- 000’oz |
38.2 |
|
44.3 |
|
| |
Yield |
- g/t |
1.3 |
|
1.1 |
|
| |
Total cash cost |
- US$/oz |
995 |
|
838 |
|
| |
Notional cash expenditure |
- US$/oz |
1,799 |
|
1,490 |
|
| |
NCE margin |
- % |
(11) |
|
12 |
|
Gold production decreased by 14 per cent from 44,300
ounces in the March quarter to 38,200 ounces in the June
quarter due to reduced mining volumes related to continued
safety concerns in the southern interface between the Juno
and Damang pit cutback. The rate of mining and access to
the traditionally higher grade areas in the Damang pit cutback
were restricted as a result of the above safety consideration.
Tonnes processed decreased from 1.22 million tonnes in the
March quarter to 0.93 million tonnes in the June quarter. In
order to improve the plant reliability the milling rate was
reduced from 630 tonnes per hour to 550 tonnes per hour. In
addition the grind size of the ore in the mill was reduced from
80 per cent passing 180 micrometre to 80 per cent passing
106 micrometre. As a consequence of these changes,
recovery improved by 1.4 per cent. As the plant is ageing,
preventative maintenance was increased to provide
sustainable processing capacity, particularly given the
increase in reserves and resources and extended mine life.
We anticipate that maintenance capital expenditure of
approximately US$20 million will be spent over the next nine
months on improving plant reliability and recovery by way of
adding an eight leach tank and upgrading the gravity circuit.
Total tonnes mined, including capital stripping, decreased
from 9.8 million tonnes in the March quarter to 8.9 million
tonnes in the June quarter. This decrease was due to the
rainy season reducing the utilisation of the mining fleet. Ore
mined decreased from 1.5 million tonnes to 1.1 million tonnes.
The strip ratio increased from 5.7 to 6.8.
Operating costs, including gold-in-process movements,
increased from US$36 million (R279 million) in the March
quarter to US$38 million (R308 million) in the June quarter, mainly due to a lower gold-in-process credit in the June
quarter compared with the March quarter. Total cash cost
increased from US$838 per ounce to US$995 per ounce
mainly as a result of lower gold produced.
Operating profit decreased from US$39 million (R302 million)
in the March quarter to US$23 million (R189 million) in the
June quarter as a result of lower revenue and increased
costs.
Capital expenditure increased from US$27 million (R211
million) in the March quarter to US$29 million (R234 million) in
the June quarter, with the majority of expenditure on prestripping,
exploration and the acquisition of mining fleet. The
high level of pre-stripping is necessary to open up the
significant reserve potential at Huni and Juno.
Notional cash expenditure increased from US$1,490 per
ounce in the March quarter to US$1,799 per ounce in the
June quarter. The NCE margin decreased from 12 per cent to
negative 11 per cent due to the lower gold production and
higher capital expenditure.
The installation of the pre-leach thickener and intensive leach
reactor, as part of the plant optimisation project, are
progressing well and are due for commissioning in the
December quarter. These enhancements should result in an
increase in gravity recovered gold, thereby improving the
overall plant yield. The revised production guidance for 2012,
at this point, is estimated at approximately 175,000 ounces.
|