South Africa region
KDC
| |
|
|
|
June
2011 |
|
| |
Gold produced |
- 000’oz |
|
272.5 |
|
| |
|
- kg |
|
8,684 |
|
8,475 |
|
| |
Yield - underground |
- g/t |
|
6.2 |
|
6.0 |
|
| |
- combined |
- g/t |
|
3.1 |
|
3.2 |
|
| |
Total cash cost |
- R/kg |
|
227,395 |
|
225,133 |
|
| |
|
- US$/oz |
|
1,003 |
|
1,033 |
|
| |
Notional cash expenditure |
- R/kg |
|
295,164 |
|
290,289 |
|
| |
|
- US$/oz |
|
1,302 |
|
1,332 |
|
| |
NCE margin |
- % |
|
11 |
|
Gold production increased from 272,500 ounces (8,475 kilograms) in
the June quarter to 279,200 ounces (8,684 kilograms) in the
September quarter. This increase was achieved despite the lost
production due to the wage-related industrial action, safety stoppages
and interventions following seismic-related events.
Underground tonnes milled decreased from 1.27 million tonnes in the
June quarter to 1.22 million tonnes in the September quarter, offset
by an increase in yield from 6.0 grams per tonne to 6.2 grams per
tonne. This increase was largely due to higher grades encountered
on the western section of the mine as well as an improved recovery.
Surface tonnes milled increased from 1.38 million tonnes to 1.58
million tonnes and the surface yield increased from 0.6 grams per
tonne to 0.7 grams per tonne.
Main development decreased by 11 per cent from 11,740 metres to
10,460 metres, while on-reef development decreased from 2,040
metres to 1,475 metres. This decrease was due to the industrial
action and the safety-related stoppages. The average development
value increased from 1,991 centimetre grams per tonne to 2,150
centimetre grams per tonne.
Operating costs increased from R1,915 million (US$282 million) to
R1,952 million (US$277 million). This increase was mainly due to one month of higher winter tariffs in the June quarter compared with two
high winter tariff months in the September quarter, annual salary
increases and higher surface-ore transport costs. Total cash cost for
the quarter increased from R225,133 per kilogram (US$1,033 per
ounce) in the June quarter to R227,395 per kilogram (US$1,003 per
ounce) in the September quarter.
Operating profit increased from R862 million (US$127 million) in the
June quarter to R1,432 million (US$204 million) in the September
quarter.
Capital expenditure increased from R545 million (US$80 million) to
R611 million (US$87 million) mainly due to timing of expenditure on
various projects and an increase in ore reserve development.
Notional cash expenditure increased from R290,289 per kilogram
(US$1,332 per ounce) in the June quarter to R295,164 per kilogram
(US$1,302 per ounce) in the September quarter as a result of the
higher capital expenditure. The NCE margin increased from 11 per
cent to 24 per cent.
Beatrix
| |
|
|
|
June
2011 |
|
| |
Gold produced |
- 000’oz |
|
98.0 |
|
| |
|
- kg |
|
2,636 |
|
3,048 |
|
| |
Yield - underground |
- g/t |
|
4.6 |
|
4.5 |
|
| |
- combined |
- g/t |
|
2.9 |
|
2.8 |
|
| |
Total cash cost |
- R/kg |
|
236,002 |
|
203,871 |
|
| |
|
- US$/oz |
|
1,041 |
|
935 |
|
| |
Notional cash expenditure |
- R/kg |
|
300,228 |
|
255,118 |
|
| |
|
- US$/oz |
|
1,325 |
|
1,170 |
|
| |
NCE margin |
- % |
|
23 |
|
Gold production decreased from 98,000 ounces (3,048 kilograms) in
the June quarter to 84,700 ounces (2,636 kilograms) in the
September quarter due to safety-related stoppages and the wagerelated
industrial action.
Underground tonnes milled decreased from 648,000 tonnes to
547,000 tonnes. The underground yield improved slightly from 4.5
grams per tonne to 4.6 grams per tonne. Surface tonnes milled
decreased from 422,000 tonnes to 352,000 tonnes. Surface yield
remained steady quarter-on-quarter at 0.3 grams per tonne.
Main development decreased from 6,682 metres in the June quarter
to 5,442 metres in the September quarter. The on-reef development
decreased from 1,673 metres to 1,182 metres due to the industrial
action and the five day stoppage after the fatal accident caused by
drilling into a misfire. The average main development value
decreased from 1,325 centimetre grams per tonne in the June
quarter to 1,109 centimetre grams per tonne in the September
quarter and reflects the value variability of the zones currently being
developed.
Operating costs were steady at R625 million (US$92 million) in the
June quarter compared with R628 million (US$89 million) in the
September quarter. Good cost control enabled annual wage
increases and winter power tariffs to be absorbed. Total cash cost
increased from R203,871 per kilogram (US$935 per ounce) to
R236,002 per kilogram (US$1,041 per ounce) due to the lower
production.
Operating profit increased from R385 million (US$56 million) in the
June quarter to R427 million (US$61 million) in the September
quarter.
Capital expenditure increased from R152 million (US$23 million) to
R163 million (US$23 million) with the majority spent on infrastructure
upgrades and ore reserve development.
Notional cash expenditure increased from R255,118 per kilogram
(US$1,170 per ounce) in the June quarter to R300,228 per kilogram (US$1,325 per ounce) in the September quarter due to the
decreased production. The NCE margin increased from 23 per cent
to 25 per cent.
South Deep project
| |
|
|
|
June
2011 |
|
| |
Gold produced |
- 000’oz |
|
76.1 |
|
| |
|
- kg |
|
2,003 |
|
2,366 |
|
| |
Yield - underground |
- g/t |
|
5.0 |
|
5.3 |
|
| |
- combined |
- g/t |
|
3.2 |
|
3.4 |
|
| |
Total cash cost |
- R/kg |
|
271,842 |
|
223,922 |
|
| |
|
- US$/oz |
|
1,199 |
|
1,027 |
|
| |
Notional cash expenditure |
- R/kg |
|
520,369 |
|
424,894 |
|
| |
|
- US$/oz |
|
2,296 |
|
1,949 |
|
| |
NCE margin |
- % |
|
(29) |
|
The South Deep capital infrastructure programme continues to meet
its key delivery dates to support the build-up to full production of
750,000 ounces. The new tailings storage facility achieved first
deposition in April this year and has now been commissioned. The
ventilation shaft deepening project remains on track for
commissioning in the September 2012 quarter and the additional rock
hoisting will build to a nameplate capacity of 195,000 tonnes per
month. This, together with the existing Main shaft capacity of
175,000 tonnes per month, will deliver the full production to the mill.
The gold plant expansion from 220,000 tonnes to 330,000 tonnes per
month is under construction, with commissioning planned in the
September 2012 quarter. The capital development has achieved 105
per cent of planned metres year to date and capital expenditure is on
track.
Gold production decreased from 76,100 ounces (2,366 kilograms) in
the June quarter to 64,400 ounces (2,003 kilograms) in the
September quarter mainly due to the wage-related industrial action.
Underground reef ore processed during the quarter decreased by 6
per cent from 419,000 tonnes to 392,000 tonnes, largely due to the
wage-related industrial action as mentioned above.
Total tonnes milled, which included 108,000 tonnes from surface
sources and 123,000 tonnes of off-reef development, decreased from
690,000 tonnes in the June quarter to 623,000 tonnes in the
September quarter. The on-reef yield decreased from 5.3 grams per
tonne to 5.0 grams per tonne mainly due to changes in mining mix.
Development decreased from 3,063 metres in the June quarter to
2,938 metres in the September quarter. The new mine capital
development in phase 1, sub 95 level, decreased from 1,173 metres
to 1,160 metres. Development in the current mine areas above 95
level decreased from 1,709 metres to 1,484 metres. Vertical
development increased from 181 metres to 294 metres. De-stress
mining increased by 23 per cent from 5,554 square metres in the
June quarter to 6,815 square metres in the September quarter.
Operating costs increased from R533 million (US$79 million) in the
June quarter to R550 million (US$78 million) in the September
quarter. The increase was mainly due to increased electricity costs,
with two winter tariff months in the quarter, and an increase in stores
cost for maintenance of mechanised equipment. Total cash cost
increased from R223,922 per kilogram (US$1,027 per ounce) to
R271,842 per kilogram (US$1,199 per ounce) in the September
quarter.
Operating profit decreased by 2 per cent from R245 million (US$36
million) in the June quarter to R240 million (US$34 million) in the
September quarter due to the 15 per cent lower gold production,
partly offset by the higher gold price received.
Capital expenditure increased from R472 million (US$69 million) in
the June quarter to R492 million (US$70 million) in the September
quarter, in line with the project plan. The majority of this capital
expenditure was on development, the ventilation shaft deepening and infrastructure, the metallurgical plant extension, trackless equipment,
as well as the full plant tailings backfill and new tailings dam facility.
Notional cash expenditure increased from R424,894 per kilogram
(US$1,949 per ounce) in the June quarter to R520,369 per kilogram
(US$2,296 per ounce) in the September quarter as a result of the
lower gold production together with increased costs and capital
expenditure.
|