Detailed and operational review
Cost and revenue optimisation initiatives through
Business Process Re-engineering
The Business Process Re-engineering programme (BPR) commenced
during the second half of calendar 2010. The BPR involves a review of
the mines’ underlying organisational structures as well as the
operational production processes from the stope to the mill. The
objective is to introduce a new business blueprint, together with an
appropriate organisational structure, which will support sustainable gold
output at an NCE margin of 20 per cent in the short to medium term
and 25 per cent in the longer term.
South Africa region
The BPR underpins the suite of M projects which were established
during financial 2008 to optimise costs and revenue over a three year
period.
Stoping full potential (Project 1M)
Project 1M is a productivity initiative that aims to improve quality mining
volumes by increasing the face advance by between 5 and 10 per cent
per annum. The BPR Stoping full potential project aims to enable the
delivery of full potential at every workface by introducing standardised
reporting and practices, and eliminating constraints.
The BPR Stoping full potential project aims to leverage advance per
blast to drive quality-volume and address the key constraints which
affect productivity on a shaft by shaft basis, including effective face
times, logistics in-flow and out-flow models and mining cycles.
This is being achieved through the following key improvement
initiatives:
- Implementation of a daily performance management routine and a suite of tools to minimise lost blasts;
- Acceleration of efforts to equip panels to improve flexibility and face length;
- Implementing improved planning and scheduling on a rolling 18 month basis for each panel;
- Optimising availability of in-stope workers through new labour management processes; and
- Addressing shaft specific key infrastructural and engineering constraints such as ventilation, hoisting and shaft schedules, and winch management and repairs.
Average face advance improved from 6.1 metres to 6.7 metres in the
June quarter. The focus will remain on improvement of flexibility and
panel availability factors for sustainable safe production.
Developing full potential (Project 2M)
Project 2M is a technology initiative aimed at mechanising all flat-end
development (i.e. development on the horizontal plane) at the long-life
shafts of KDC and Beatrix. South Deep is already a fully mechanised
mine. The aim of the project is to improve safety and productivity,
reduce development costs and increase ore reserve flexibility through
higher monthly development advance rates.
The flat-end metres advance achieved by mechanised means was
similar to the previous quarter at 86 per cent. Planning is being
optimised in such a manner that a drill rig can service multiple ends to
improve utilisation of the rig and thus improve strike rate and efficiency.
NCE full potential (Project 3M)
The BPR NCE full potential project focuses on all categories of spend.
The first phase of the BPR initiatives, which commenced in the second
half of calendar 2010 in South Africa and included the merger of the
Kloof and Driefontein operations, now known as KDC, was concluded
at the end of December 2010.
In the second phase of the project, targeted cost reductions of between
R500 million (US$68 million) and R1.0 billion (US$137 million) have
been scheduled for KDC and Beatrix for the period to December 2012.
These cost saving initiatives are to be achieved through various
programmes which include productivity improvement initiatives,
continued reduction in staff through natural attrition and voluntary
separation, and power cost savings initiatives. This will assist in
absorbing some of the inflationary pressures faced in terms of input
costs.
A key priority is a fit for purpose structure at South Deep which is:
- consistent with the new regional structure and principles;
- appropriate for the ramp-up; and
- customised for bulk trackless mechanised mining.
The completion of this work is a key deliverable in 2011.
The intent with BPR in 2011 is to mitigate as much of the anticipated
mining inflation increases as possible. Cost reductions of R35 million
were achieved in the June quarter, resulting in savings of R294 million
since the initiative started in mid-2010. These savings were mainly
achieved by changing to a more cost effective underground mining
support regime, a reduction in staff through natural attrition and the
voluntary separation programme, a reduction in non-specialised
contractors and power cost saving initiatives.
Project 4M
Project 4M focuses on the Mine Health and Safety Council (MHSC)
milestones agreed to on 15 June 2003 at a tripartite health and safety
summit, comprising representatives from Government, organised
labour and mining companies. The focus is on achieving occupational
health and safety targets and milestones over a 10-year period. The
commitment was driven by the need to achieve greater improvements
in occupational health and safety in the mining industry.
One of the milestone targets is that no machine or piece of equipment
may generate a sound pressure level in excess of 110dB(A) after December 2013. In order to achieve this target the company is focusing
on reducing the noise at source.
The number of measurements expressed as a percentage of noise
measurements of machinery/equipment emitting noise in excess of
110dB (A) is currently 0.3 per cent. Silencing of equipment is ongoing
and each intervention is project managed.
Silicosis remains one of the biggest health risks associated with the
gold mining industry. In order to meet the silicosis targets the company
has several interventions in place, which include:
- the upgrading of tip filters by either replacing complete units or
installing additional first stage pre-filtration systems to increase dust
filtration efficiency by removing larger particles of dust before they
enter the primary dust filtration unit (improved from 94 per cent to
99 per cent implementation to date across the South African
region);
- the use of foggers to trap dust particles liberated from tipping points
before dust enters the main air stream (similar at 83 per cent
implementation to date across the South African region);
- footwall treatment to bind dust on the footwall and prevent it from
being liberated into the intake airways (similar at 100 per cent
implementation to date across the South African region); and
- installation of tip doors. The tip doors are installed into the tipping
points and remain closed when no tipping is taking place, thus
reducing dust from entering the intake airways. The tip doors being
spring loaded are self-closing once tipping is completed (improved
from 54 per cent to 60 per cent implementation to date across the
South African region).
It must be noted that although the footwall treatment was completed in
all identified areas, periodic retreatment is required to maintain
effectiveness. The re-treatment is 35 per cent completed.
Of the individual gravimetric dust sample measurements taken during
the June quarter, 98 per cent of individual samples were below the
occupational exposure limit of 0.1 milligrams per cubic metre, thus
meeting the target of not less than 95 per cent.
In March 2011, the South African Constitutional Court ruled that
legislation which limited employees’ rights to claim compensation for
certain diseases, including silicosis, were unconstitutional. As a result,
the Court found that employees had the right to sue employers for
common law damages to the extent that such employees could prove
that they had suffered loss as a result of the negligence of the employer
and such loss could be quantified. The potential impact to the Group is
being assessed. In addition, we are reviewing our current processes to
determine what additional measures can be taken to further mitigate
the risks to employees of contracting silicosis.
West Africa region
Tarkwa
The June quarter has seen the consolidation of several productivity and
efficiency initiatives at Tarkwa which has resulted in savings of US$6
million on BPR initiatives for the quarter. The main contributors were
cost reductions and drill yield improvement, i.e. increased volume
blasted per drill metre. The increased drill yield was achieved by using
stronger explosives, increasing the burden and spacing of drill patterns,
while maintaining fragmentation performance and increasing the
blasted capital waste bench height from 6 metres to 9 metres. This
resulted in a US$2 million cost reduction against the 2010 baseline.
The removal of bottlenecks at the North Heap leach facility has seen a
10 per cent improvement in tonnes processed against plan for the June
quarter. This was mainly due to a reduction in operational and
mechanical down time and the installation of three new large tertiary
crushers commissioned during May. Metallurgical initiatives focused on
improving recovery in the CIL plant. During the June quarter strategic
sourcing and renegotiation of supply agreements for basic chemicals,
explosives, grinding media and mill liners resulted in US$1 million
spend reduction on these items against the 2010 baseline. Drill and
blast efficiencies have improved by 20 per cent by optimising drill and
blast design parameters.
Focus for the September quarter will be directed at removing
bottlenecks from the mining operations and improving gold recovery at
the North Heap leach facility. This will be achieved by improving utilisation and availability of mining equipment in order to maximise
quality ore supply from the open pit to the processing plants and
improve capital strip tonnages. At the North Heap leach facility the
focus will be on optimising particle size distribution for maximum gold
liberation from crushed ore placed on the North Heap leach facility as
well as reducing gold in process currently on heaps, targeting a 10 per
cent reduction over the next two quarters.
Damang
Focus during the quarter was on harnessing the benefits realised from
the conversion from contractor to owner operation and owner
maintenance. To date, benefits of US$9 million were achieved of which
US$7 million were realised in the June quarter.
Phase 2 of the BPR commenced during the June quarter with the
completion of a full review of further potential improvement initiatives.
The focus during the September quarter will be on implementing the
first phase of these additional improvement projects.
Australasia region
St Ives
The focus at St Ives has been on direct costs and productivity
improvements within the existing site arrangements, including
improvements in the heap leach operation, Lefroy mill area and shortterm
interval controls in both the underground and open pit operations.
The second point of focus involved detailed planning and
implementation of owner mining for all underground ore extraction,
while still maintaining the contractor development model similar to
Agnew.
Recently an agreement was reached with the primary underground
contractor to acquire a major portion of its site based employees,
mining fleet and associated equipment required to facilitate the
transitioning into an owner mining operation. This transition will be
completed during the September 2011 quarter.
Further studies in the opportunities afforded by owner mining are being
undertaken at St Ives in other contractor areas to improve the cost
structure and productivities. A resource optimisation study is currently
in progress to identify further improvements in mine scheduling.
Agnew
At Agnew the main focus has been on securing productivity
improvements from the implementation of owner mining in mid-2010.
This required focus on short-term interval control at the underground
operations, allowing for improved scheduling of equipment and
resources. This was a major contributor to a 25 per cent increase in
tonnes extracted from the underground mines in the June quarter
compared with the March quarter.
In addition, it was determined that a move from contractor to owner
maintenance would also lead to cost improvements. This change was
implemented during the June quarter. Currently contractors are only
used for underground development activities.
|