Tarkwa gold mine - Mineral Resources and Mineral Reserves

The year-on-year Mineral Resources and Mineral Reserves have changed by -5% and -3% respectively, as a result of mining depletion, resource model and mine design changes, inclusions and cost input updates.

Stockpile tonnage and grade estimates are based on accumulations of estimated tonnage and grades trucked throughout the history of the mine, and are therefore considered to be reasonably accurate. However, the grades and tonnages are discounted by 5% for processing purposes, as experience has shown that this is realistically achievable when reclaiming a stockpile. Unless otherwise stated, all Mineral Resources and Mineral Reserves are quoted as 100% managed and are not attributable with respect to ownership.

Mineral Resources

The Mineral Resource and Mineral Reserve estimates have been updated using the current Gold Fields planning gold price of US$1,400/oz and US$1,200/oz respectively and reported in accordance with the SAMREC Code. The surface sources include stockpiles that are supported by adequate sampling, and are thus classified as Measured Mineral Resources, plus the South Heap Leach material, which is classified as Indicated.

Mineral Resources are quoted at an appropriate in situ economic cut-off grade, with tonnages and grades based on the resource block model. They also include estimates of any material below the cut-off grade that is required to be mined in order to extract the complete pay portion of the Mineral Resource.

Mineral Resource classification

  Tonnes (kt)     Grade (g/t)     Gold (koz)  
Classification Dec 2017 Dec 2016 Dec 2015     Dec 2017 Dec 2016 Dec 2015     Dec 2017 Dec 2016 Dec 2015  
Open pit and underground                            
Measured 58,700 66,833 70,439     1.45 1.47 1.47     2,741 3,160 3,324  
Indicated 108,342 110,820 117,029     1.33 1.33 1.33     4,634 4,746 5,015  
Inferred 5,497 5,577 4,752     1.18 1.17 1.13     209 210 172  
Total in situ 172,538 183,230 192,220     1.37 1.38 1.38     7,584 8,116 8,511  
Surface                            
Measured stockpiles 12,245 8,440 6,588     0.77 0.76 0.72     303 207 152  
South Heap Leach (Indicated) 59,977 59,977 59,977     0.40 0.40 0.40     771 771 771  
Total surface 72,222 68,416 66,565     0.46 0.44 0.43     1,074 978 924  
Grand total 244,760 251,646 258,785     1.10 1.12 1.13     8,658 9,094 9,435  

Mineral Resource classification per mining area

  Measured   Indicated   Inferred   Total Mineral Resource
Open pit Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
  Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
  Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
  Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
Akontansi 20,465 1.29 847   82,409 1.28 3,394   4,411 1.10 157   107,285 1.28 4,398
Kottraverchy 9,982 1.66 533   71 1.01 2         10,053 1.66 535
Pepe/Mantraim 10,042 1.43 462   5,887 1.18 223   561 1.44 26   16,490 1.34 711
Teberebie 18,211 1.54 899   19,974 1.58 1,015   525 1.57 26   38,710 1.56 1,940
Total open pit 58,700 1.45 2,741   108,342 1.33 4,634   5,497 1.18 209   172,538 1.37 7,584
Surface                              
Spent Ore (South Heap Leach)   59,977 0.40 771     59,977 0.40 771
 
                             
Surface stockpiles 12,245 0.77 303       12,245 0.77 303
Total surface 12,245 0.77 303   59,977 0.40 771     72,222 0.46 1,074
Grand total 70,945 1.33 3,044   168,319 1.00 5,405   5,497 1.18 209   244,760 1.10 8,658

Modifying factors

  • The Measured and Indicated Mineral Resources are inclusive of those Mineral Resources modified to produce Mineral Reserves in the LoM plan
  • All Mineral Reserves are quoted in terms of RoM grades and tonnages as delivered to the metallurgical processing facilities and are therefore fully diluted
  • Unless otherwise stated, all Mineral Resources and Mineral Reserves are quoted as 100% managed and are not attributable with respect to ownership
  • Mineral Resources and Mineral Reserves undergo regular internal and/or external audits, and any issues identified are rectified at the earliest opportunity
        December      
  Units   2017   2016   2015  
Mineral Resource parameters
Mineral Resource gold price US$/oz   1,400   1,400   1,500  
Cut-off for mill feed g/t   0.37   0.4   0.38  
Mineral Reserve parameters
Mineral Reserve gold price US$/oz   1,200   1,200   1,300  
Cut-off for mill feed g/t   0.44   0.47   0.45  
Mining recovery factor (open pit) %   100   100   100  
Strip ratio (waste:ore) ratio   5.0   5.1   5.4  
MCF %   98   98   98  
Dilution open pit1 cm   30/20   30/20   30/20  
Plant recovery factor - CIL %   97.0   97.0   97.0  
CIL processing capacity Mtpa   13.7   13.5   13.5  

1 Refers to 30cm hangingwall and 20cm footwall dilution respectively

Grade tonnage curve

Grade tonnage curve for the entire open pit Mineral Resource is presented below

  Grade tonnage curve - Surface
 

Mineral Reserves

The Mineral Reserve estimate for Tarkwa gold mine is based on the development of appropriately detailed and engineered LoM plans. All design and scheduling work is undertaken to an applicable level of detail by experienced engineers using mine-planning software. The planning process incorporates realistic modifying factors and the use of appropriate cut-off grades, geotechnical criteria, mining fleet productivities and other techno-economic investigations.

Mineral Reserve statements include only Measured and Indicated Mineral Resources modified to produce Mineral Reserves contained in the LoM plan. This declaration is based on the premise that all the ore will be treated through the CIL plant.

Mineral Reserve classification

  Tonnes (kt)     Grade (g/t)     Gold (koz)  
Classification Dec 2017 Dec 2016 Dec 2015     Dec 2017 Dec 2016 Dec 2015     Dec 2017 Dec 2016 Dec 2015  
Open pit                            
Proved 40,464 53,542 63,266     1.26 1.28 1.30     1,644 2,200 2,635  
Probable 82,015 74,150 81,506     1.21 1.22 1.22     3,188 2,903 3,187  
Total open pit 122,479 127,692 144,773     1.23 1.24 1.25     4,832 5,104 5,822  
Surface                            
Proved stockpiles 12,245 8,440 6,588     0.77 0.76 0.72     303 207 152  
South Heap Leach (Probable)   59,977   59,977   59,977       0.40   0.40   0.40       771   771   771  
Total surface 72,222 68,416 66,565     0.46 0.44 0.43     1,074 978 924  
Grand total 194,701 196,108 211,338     0.94 0.96 0.99     5,906 6,082 6,746  

Mineral Reserve classification per mining area

  Proved     Probable     Total Mineral Reserve  
Mining area Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
    Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
    Tonnes
(kt)
Grade
(g/t)
Gold
(koz)
 
Open pit                            
Akontansi 14,402 1.09 504     61,334 1.14 2,250     75,735 1.13 2,753  
Kottraverchy 4,413 1.39 198         4,413 1.40 198  
Pepe/Mantraim 6,467 1.30 271     1,162 1.05 39     7,629 1.26 310  
Teberbie 15,183 1.38 672     19,519 1.43 899     34,702 1.41 1,570  
Total open pit 40,464 1.26 1,644     82,015 1.21 3,188     122,479 1.23 4,832  
Surface                            
Spent ore (SHL)     59,977 0.40 771     59,977 0.40 771  
Surface stockpiles 12,245 0.77 303         12,245 0.77 303  
Total surface stockpiles   12,245   0.77   303       59,977   0.40   771       72,222   0.46   1,074  
Grand total 52,709 1.15 1,947     141,991 0.87 3,959     194,701 0.94 5,906  

Mineral Resource and Mineral Reserve reconciliation year-on-year

Factors that affected Mineral Resource year-on-year Factors that affected Mineral Reserve year-on-year
Depletion by mining   Depletion by mining
Updated economic factors   Improved costs
Mineral Resource model updates, predominately at Akontansi and PAMTA   Mineral Resource model updates
    Re-optimisation/re-engineering of pit designs at Teberebie and Akontansi

Mineral Resource reconciliation (Gold – koz)   Mineral Reserve reconciliation (Gold – koz)
 

Mineral Reserve sensitivity

The Mineral Reserve sensitivity has been derived from the application of the relevant cut-off grades to individual grade tonnage curves of the optimised pit shells for the open pits.

The Mineral Reserve sensitivities are not based on detailed depletion schedules and should be considered on a relative and indicative basis only. The following graphs indicate the Managed Mineral Reserve sensitivity at -15%, -10%, -5%, base (US$1,200/oz), +5%, +10%, and +15% to the gold price.

  Mineral Reserve sensitivity (Gold – Moz)